[FONT=&]"If you look at the renderings it was supposed to be a cable stayed bridge. They released the supports under the slab without the tower/cables installed."
[/FONT]
Yes, this.
I looked at the renderings as well.....the tension cables were to balance the compression forces and weight.
Yet the bridge was swung over on its own? Was it expected that the concrete slab would be temporarily strong enough for that span without a support in place before the tower and cables were to be placed?
I don't understand.
And the stress test...what were they thinking to allow traffic through during that?
Wow. Thanks. I didn't realize that about the design.
Any engineers on the thread? Why would they test it before they installed the cables?